Jakarta and Tokyo move faster on Masela project to strengthen long-term energy security
Indonesia and Japan are fast-tracking the Abadi Gas Field project in Maluku as global energy risks intensify amid worsening conflict in the Middle East. The renewed push signals how geopolitical instability is reshaping major energy decisions in Asia.
Strategic Energy Project Gains Urgency
Indonesia and Japan have reached a high-level agreement to accelerate development of the Abadi Gas Field in the Masela Block, Maluku, as concerns grow over energy security during the ongoing conflict involving the United States, Israel, and Iran. The project is increasingly seen as a strategic response to potential supply disruptions and the need for more secure energy corridors in the region.
Jakarta Confirms Progress On Major Investment
SKK Migas head Djoko Siswanto confirmed on March 30, 2026, that all parties had agreed to speed up the project, adding that the US$20 billion investment remains on a positive track. The agreement became a key point during President Prabowo Subianto’s state visit to Japan, where he was accompanied by Energy and Mineral Resources Minister Bahlil Lahadalia. According to the ministry, Bahlil’s presence was aimed at turning diplomatic momentum into concrete energy deals that can support Indonesia’s national energy security.
Japan Partnership Strengthens Project Timeline
The push followed an earlier meeting this month between Minister Bahlil and Inpex Corporation chief executive Takayuki Ueda. The project is already 25 percent complete and is expected to become a major economic driver for Eastern Indonesia while serving as a critical future gas supply source for domestic industrial development. Indonesian Ambassador to Japan Nurmala Kartini Sjahrir described the agreement as a historic milestone, with the Indonesian Embassy in Tokyo now helping facilitate scheduling to keep the project moving.
FEED And Tender Plans Are Being Advanced
A major near-term target is to complete the Front-End Engineering and Design, or FEED, phase by the third quarter of 2026, a timeline considered crucial for meeting the planned production window of 2029 to 2030. Minister Bahlil has also pushed for the FEED stage to be advanced to the second quarter of 2026. That move would allow Engineering, Procurement, and Construction tenders to run in parallel, potentially cutting lead time for one of Indonesia’s biggest deep-water gas projects.
Broader Stakes For Indonesia And The Region
The Abadi Gas Field is more than a commercial energy project. It reflects Indonesia’s wider effort to secure long-term energy supplies, attract strategic investment, and strengthen Eastern Indonesia’s role in national development. At a time when global conflicts are affecting commodity flows and energy planning, the Masela project is becoming a symbol of how Indonesia is positioning itself for a more uncertain geopolitical and economic landscape.
The acceleration of the Abadi Gas Field project shows how energy security is becoming a bigger priority as global tensions deepen. For Indonesians, the project could help strengthen domestic supply, support industrial growth, and bring greater economic activity to Eastern Indonesia. For Singaporeans, it underscores how regional stability, cross-border investment, and energy infrastructure are becoming increasingly interconnected as Asian nations respond to global supply risks.